In software projects, it is most important to measure the quality, cost and effectiveness of the project and the processes. Without measuring these, project can’t be completed successfully. This uses Software Test Metrics and Measurements to measure.

There is a famous statement: “We can’t control things which we can’t measure”.

Here controlling the projects means, how a project manager/lead can identify the deviations from the test plan ASAP in order to react in the perfect time. Generation of test metrics based on the project needs is very much important to achieve the quality of the software being tested.

What are Software Testing Metrics?

A Metric is a quantitative measure of the degree to which a system, system component, or process possesses a given attribute. 

Software Test Metrics and Measurements: can be defined as “STANDARDS OF MEASUREMENT”.

Software Metrics are used to measure the quality of the project. Simply, Metric is a unit used for describing an attribute. Metric is a scale for measurement.

Suppose, in general, “Kilogram” is a metric for measuring the attribute “Weight”. Similarly, in software, “How many issues are found in thousand lines of code?”, here No. of issues is one measurement & No. of lines of code is another measurement. Metric is defined from these two measurements.

Test metrics example:

  • How many defects are existed within the module?
  • How many test cases are executed per person?
  • What is the Test coverage %?

What is Software Test Measurement?

Measurement is the quantitative indication of extent, amount, dimension, capacity, or size of some attribute of a product or process.

Test measurement example: Total number of defects.

Please refer below diagram for clear understanding of the difference between Measurement & Metrics.

Why Software Test Metrics and Measurements?

Generation of Software Test Metrics is the most important responsibility of the Software Test Lead/Manager.

Test Metrics are used to,

  1. Take the decision for next phase of activities such as, estimate the cost & schedule of future projects.
  2. Understand the kind of improvement required to success the project
  3. Take decision on process or technology to be modified etc.

Importance of Software Testing Metrics:

As explained above, Test Metrics are the most important to measure the quality of the software.

Now, how can we measure the quality of the software by using Metrics?

Suppose, if a project does not have any metrics, then how the quality of the work done by a Test analyst will be measured?

For Example: A Test Analyst has to,

  1. Design the test cases for 5 requirements
  2. Execute the designed test cases
  3. Log the defects & need to fail the related test cases
  4. After the defect is resolved, need to re-test the defect & re-execute the corresponding failed test case.

In above scenario, if metrics are not followed, then the work completed by the test analyst will be subjective i.e. the test report will not have the proper information to know the status of his work/project.

If Metrics are involved in the project, then the exact status of his/her work with proper numbers/data can be published.

I.e. in the Test report, we can publish:
1. How many test cases have been designed per requirement?
2. How many test cases are yet to design?
3. How many test cases are executed?
4. How many test cases are passed/failed/blocked?
5. How many test cases are not yet executed?
6. How many defects are identified & what is the severity of those defects?
7. How many test cases are failed due to one particular defect? etc.

Based on the project needs we can have more metrics than above mentioned list, to know the status of the project in detail.

Based on the above metrics, test lead/manager will get the understanding of the below mentioned key points.
a) %ge of work completed
b) %ge of work yet to be completed
c) Time to complete the remaining work
d) Whether the project is going as per the schedule or lagging? etc.

Based on the metrics, if the project is not going to complete as per the schedule, then the manager will raise the alarm to the client and other stake holders by providing the reasons for lagging to avoid the last minute surprises.

Metrics Life Cycle:

Types of Manual Software Test Metrics and Measurements:

Testing Metrics are mainly divided into 2 categories.

  1. Base Metrics
  2. Calculated Metrics

Base Metrics:
Base Metrics are the Metrics which are derived from the data gathered by the Test Analyst during the test case development and execution.

This data will be tracked throughout the Test Life cycle. I.e. collecting the data like, Total no. of test cases developed for a project (or) no. of test cases need to be executed (or) no. of test cases passed/failed/blocked etc.

Calculated Metrics:
Calculated Metrics are derived from the data gathered in Base Metrics. These Metrics are generally tracked by the test lead/manager for Test Reporting purpose.

Examples of Software Test Metrics and Measurements:

Let’s take an example to calculate various test metrics used in software test reports:

Below is the table format for the data retrieved from the test analyst who is actually involved in testing:

Definitions and Formulas for Calculating Metrics:

#1) %ge Test cases Executed: This metric is used to obtain the execution status of the test cases in terms of %ge.

%ge Test cases Executed = (No. of Test cases executed / Total no. of Test cases written) * 100.

So, from the above data,
%ge Test cases Executed = (65 / 100) * 100 = 65%

#2) %ge Test cases not executed: This metric is used to obtain the pending execution status of the test cases in terms of %ge.

%ge Test cases not executed = (No. of Test cases not executed / Total no. of Test cases written) * 100.

So, from the above data,
%ge Test cases Blocked = (35 / 100) * 100 = 35%

————

#3) %ge Test cases Passed: This metric is used to obtain the Pass %ge of the executed test cases.

%ge Test cases Passed = (No. of Test cases Passed / Total no. of Test cases Executed) * 100.

So, from the above data,
%ge Test cases Passed = (30 / 65) * 100 = 46%

#4) %ge Test cases Failed: This metric is used to obtain the Fail %ge of the executed test cases.

%ge Test cases Failed = (No. of Test cases Failed / Total no. of Test cases Executed) * 100.

So, from the above data,
%ge Test cases Passed = (26 / 65) * 100 = 40%

#5) %ge Test cases Blocked: This metric is used to obtain the blocked %ge of the executed test cases. A detailed report can be submitted by specifying the actual reason of blocking the test cases.

%ge Test cases Blocked = (No. of Test cases Blocked / Total no. of Test cases Executed) * 100.

So, from the above data,
%ge Test cases Blocked = (9 / 65) * 100 = 14%

#6) Defect Density = No. of Defects identified / size

(Here “Size” is considered as requirement. Hence here the Defect Density is calculated as number of defects identified per requirement. Similarly, Defect Density can be calculated as number of Defects identified per 100 lines of code [OR] No. of defects identified per module etc.)

So, from the above data,
Defect Density = (30 / 5) = 6

#7) Defect Removal Efficiency (DRE) = (No. of Defects found during QA testing / (No. of Defects found during QA testing +No. of Defects found by End user)) * 100

DRE is used to identify the test effectiveness of the system.
Suppose, During Development & QA testing, we have identified 100 defects.
After the QA testing, during Alpha & Beta testing, end user / client identified 40 defects, which could have been identified during QA testing phase.

Now, The DRE will be calculated as,
DRE = [100 / (100 + 40)] * 100 = [100 /140] * 100 = 71%

$8) Defect Leakage: Defect Leakage is the Metric which is used to identify the efficiency of the QA testing i.e., how many defects are missed / slipped during the QA testing.

Defect Leakage = (No. of Defects found in UAT / No. of Defects found in QA testing.) * 100

Suppose, During Development & QA testing, we have identified 100 defects.
After the QA testing, during Alpha & Beta testing, end user / client identified 40 defects, which could have been identified during QA testing phase.

Defect Leakage = (40 /100) * 100 = 40%

#9) Defects by Priority: This metric is used to identify the no. of defects identified based on the Severity / Priority of the defect which is used to decide the quality of the software.

%ge Critical Defects = No. of Critical Defects identified / Total no. of Defects identified * 100
From the data available in the above table,
%ge Critical Defects = 6/ 30 * 100 = 20%

%ge High Defects = No. of High Defects identified / Total no. of Defects identified * 100
From the data available in the above table,
%ge High Defects = 10/ 30 * 100 = 33.33%

%ge Medium Defects = No. of Medium Defects identified / Total no. of Defects identified * 100
From the data available in the above table,
%ge Medium Defects = 6/ 30 * 100 = 20%

%ge Low Defects = No. of Low Defects identified / Total no. of Defects identified * 100
From the data available in the above table,
%ge Low Defects = 8/ 30 * 100 = 27%

Recommended reading => How to Write an Effective Test Summary Report

Conclusion:

The metrics provided in this article are majorly used for generating the daily/weekly status report with accurate data during test case development/execution phase & this is also useful for tracking the project status & Quality of the software.

  • How to Become a Data Analyst – Salary, Qualifications, skills.
    How to Become a Data Analyst – Salary, Qualifications, skills. Hello, hope you are doing great. Let’s start by defining what a data analyst is? Whether it’s sales figures, audience demographics, and market research,…
  • The truth about Crypto-Currency.
    The truth about Crypto-Currency.  What to Know About Cryptocurrency. What is cryptocurrency? Cryptocurrency is a type of digital currency that generally only exists electronically. There is no physical coin or bill unless you use…
  • Basic Computer Operations
    Basic Computer Operations. A computer as shown in the figure below performs basically five major operations or functionsirrespective of its size and make. These are 1) it accepts data or instructions by way of…
  • Classification of Computers
    Classification of Computers. i. Classification of Computers by Size a) Micro-Computers • Micro –Computers are the Smallest class of Computers• Micro- Computers have one micro-processor in its Central Processing Unit• Micro-Processor refers to Central…
  • History of Computers
    History of Computers i. First generation computers (1946-1956) Overview of the Intelligent System They made use of vacuum tubes to store and process information. The tubesconsumed a lot of power and generated a lot…
Related posts
Computer ScienceGUITechUX

How to Become a Data Analyst - Salary, Qualifications, skills.

4 Mins read
How to Become a Data Analyst – Salary, Qualifications, skills. Hello, hope you are doing great. Let’s start by defining what a data analyst is? Whether it’s sales figures, audience demographics, and market research, or…
BusinessComputer ScienceTech

The truth about Crypto-Currency.

5 Mins read
The truth about Crypto-Currency.  What to Know About Cryptocurrency. What is cryptocurrency? Cryptocurrency is a type of digital currency that generally only exists electronically. There is no physical coin or bill unless you use a…
Computer ScienceTechUX

Basic Computer Operations

2 Mins read
Basic Computer Operations. A computer as shown in the figure below performs basically five major operations or functionsirrespective of its size and make. These are 1) it accepts data or instructions by way of input,…

Leave a Reply

Your email address will not be published. Required fields are marked *